Project:
|
Coordinated IT Requirements with Architect and
Managed Move to New Building
|
Client:
|
Decision
Support Systems
|
Benefit:
|
Data center space built to suit the
company's current and potential future needs for space,
HVAC, power, and telecommunications access. All remote
offices came online Monday morning after the move
without incident, end user equipment was redeployed
without issue and telephone system deployment had only
minor annoyance dialing plan issues. |
Highlights
|
|
|
-
The
firm had a 40,000 square foot facility built to suit
for office, data center and warehouse space to
support the firm's national distribution
requirements.
-
I
worked with the architects from initiation regarding
IT's requirements for space, power, backup
generator, communications capacity and access, and
HVAC capacity to ensure that the 3 year growth plan
could be accommodated without any significant
capacity changes in the infrastructure.
-
I
redesigned the core and distribution networking
environment including cable plant design and
equipment specifications.
-
The
data center move went flawlessly. All systems,
Windows, Unix, Solaris, Oracle Financials, came up
in the environment with no problems.
-
End
user's PCs moved with minimal issues - the most
serious coming from rough handling by the moving
crew. The computing environment was 100% available
to in-house users Monday morning after the move. One
branch office had an issue with Exchange to Exchange
server connections and handshaking that was easily
resolved.
|
|
|
|
|
|
|
|